E. Hillsdale Boulevard Street Rehabilitation

Project Area:  East Hillsdale Boulevard between S. Norfolk Street and 500 feet west of the intersection with Saratoga Drive.

Project Description: Resurface the roadway from S. Norfolk Street past Saratoga Drive. Additional improvements include the extension of the left turn lane from Hillsdale on to Saratoga, ADA-compliant curb ramp upgrades, and crosswalk modifications.  

Project schedule: On hold through winter months 2018

Anticipated Work Hours: (Subject to change for emergencies)

General construction will be performed during the day. However, to minimize traffic impacts and as the project street is heavily utilized to access and exit Highway 101, the contractor is required to perform grinding and paving operations, installation of traffic striping and traffic loops at night.  

  • Normal Operations: Monday to Friday (8 a.m. to 5 p.m.)
  • Grinding and Paving Operations (night work): Sunday to Friday (9 p.m. to 5 a.m.) 

Contract Duration: Work is expected to begin on October 1 and last approximately 40 working days.

City Contact:

Jimmy Vo

Construction Manager

 650-522-7319

This project is funded by SB1. Click the link below to find out more. 