Go To Search
30th Avenue Street Reconstruction Project
30th Notification MapShort Description of Project:

The Department of Public Works is implementing a street reconstruction project at 30th Avenue from Alameda de las Pulgas to Flores Street. 

This project consists of “street reconstruction” of pavement section up to 24 inches in depth from lip of gutter to lip of gutter; ovelay 4.5 inches of asphalt concrete pavement; install wheelchair ramps where applicable; repair concrete curb & gutter, driveway approach and sidewalk as necessary to maintain stormwater surface runoff within the project limits.

“Street Reconstruction” - Generally includes the removal of all existing asphalt surfacing, excavation of the road subgrade materials, and replacement of storm and sewer as necessary.  The road is re-built from the bottom-up, with new aggregate base and new asphalt concrete pavement.

Upcoming Work (update as of November 3, 2016):

Redgwick Construction Company (Contractor) is contracted with the City of San Mateo, Public Works Department for the 30th Avenue Street Reconstruction Project.
 

The Contractor will perform the following work in your neighborhood: Concrete improvements (which may include driveway approach, sidewalk, curb & gutter, and wheel chair access ramps), asphalt concrete street reconstruction work, and storm pipe work.

Traffic Advisories - Impacted Streets: Delay up to 30 minutes
30th Avenue from Flores Street to Alameda de las Pulgas

(Road closure as follow: estimate one street segment at a time; side streets will be impacted in close proximity to the intersections)

-          30th Avenue & Alameda de las Pulgas
-          30th Avenue & Isabelle Avenue

-          30th Avenue & Juniper Street

-          30th Avenue & Hacienda Street

-          30th Avenue & Flores Street

Construction Duration:
In November 2016, the contractor is scheduled to perform concrete work, followed by a cement treated road base stabilization process for 30th Avenue, from Flores Street to Alameda de las Pulgas.  The project will then continue through January 2017 (weather permitting).

There will be no construction activity on the following dates: November 24-26, December 24-26, December 31-January 2, and January 16.


Work Hours:

Monday – Friday: 8:00 a.m. to 4:30 p.m.
Saturday: 9:00 a.m. to 5:00 p.m.


Construction Activities:

Concrete repair work will take place on one side of the street at a time to provide pedestrian access along 30th Avenue.  Concrete work repair locations will be marked with “white” paint.  Curbside parking is restricted during construction and at least 7 days post construction work to allow time for concrete curing.

Street pavement reconstruction will be performed in three sections: Flores to Hacienda, Hacienda to Isabelle, and Isabelle to Alameda de las Pulgas.  Each section will be milled open to the depth of up to 14 inches for up to five (5) consecutive days.  Road closure and traffic control will be implemented during work hours to assist traffic detour around the neighborhood.  Private driveways within the section under reconstruction work will not be accessible during work hours.  The street segment under construction will be re-opened at the end of each working day.  There will be uneven pavement at the driveway approaches.  The Contractor will provide a temporary ramp with a 4:1 slope at the street and driveway approaches for vehicle access during non-working hours.  Active vehicles must exit private driveways before 7:30 a.m. within the street segment under construction.  Vehicles must be parked on adjacent streets or on other street segments where reconstruction work is not occurring during that period.  Construction notices (door hanger) will be provided at least three (3) days before street pavement reconstruction work.

The Contractor will set up detours on 30th Avenue, Flores Street, Hacienda Street, Juniper Street, Isabelle Avenue, and Alameda de las Pulgas.  Detour & traffic signs will be posted to assist traffic access around the work area.  Please expect delays up to 30 minutes when accessing this neighborhood.

Please note that trash and recycling collection will be delayed.  The Contractor will assist garbage pick-ups.  To ensure collection, please place the garbage and recycling containers at the edge of the road or in the driveway the evening prior.

During the time it takes the contractor to reconstruct the streets, the City and the Contractor request your cooperation in observing the following:

-          Maintain 5 mph speed limits when accessing the neighborhood.

-          Follow traffic signage posted in the neighborhood.

-          Park your vehicles away from the construction zone.

-            Allow extra travel time for access. Persons with disabilities that require accommodation should contact Jai Raj, Field Engineer, at (650) 522-7375.


The City understands that the utility relocation work and the street reconstruction project have caused inconveniences for the residents.  The City appreciates your patience and thanks you for your cooperation.


The following contact information is provided for your convenience.  Please feel free to call us if there are any issues or concerns that you have regarding this project.


City of San Mateo, Department of Public Works

Jai Raj, Field Engineer
Office: (650) 522-7375

Redgwick Construction Company
Mateen Rooshen, Project Manager
Cell: (925) 470-6675
    OR
Phew Thao, Project Engineer
Cell: (916) 380-2133
    OR
Juan Mora, Project Foreman
Cell: (510) 303-5578


San Mateo City Hall – 330 West 20th Avenue, San Mateo, CA 94403

CivicPlus Content Management System © 1997- CivicPlus. All rights reserved.
All content © 2006- San Mateo, CA and its representatives. All rights reserved.