Los Prados Sanitary Sewer Relief Project
Name of Project: Los Prados Sanitary Sewer Relief Project
Impacted Areas: Norfolk Street, from Fashion Island Blvd. to Lodi Avenue, Lodi Avenue and Meadowview Place
Expected to Commence: August 2010
Expected to Finish: March 2011
Work Hours: 8:00am - 5:00pm, Monday - Friday
Short Description of Work: Installation of a new sewer pipe in the public right-of-way (Norfolk Street) to increase sewer capacity.
Benefits of Work: Reduce chances of sanitary sewer overflows
Expected Impacts: Traffic delays on Norfolk Street and noise during construction
General Contractor:
Shaw Pipelines
Main Office: (415) 337-0910
Project Manager:
Evan Albert, Associate Engineer
(650) 522-7319