South Trunk Sanitary Sewer Relief Project
Name of Project: South Trunk Sanitary Sewer Relief Project
Impacted Areas:
- Delaware: 25th Avenue to Sunnybrae Boulevard
- Sunnybrae Blvd: Delaware to S. Amphlett Boulevard
- Under Highway 101: S. Amphlett Boulevard to Patricia Avenue
Expected to Commence: Construction will be completed in phases. Phase 1 is anticipated to commence in Summer 2012.
Expected to Finish: All phases expected to finish by late 2014.
Work Hours: 7:30am - 5:00pm, Monday - Friday. Possible night work.
Short Description of Work: Installation of a sewer relief line that will carry wet weather flows from the Southwest area of San Mateo to the City’s Dale Avenue pump station.
Benefits of Work: The completion of this project will alleviate sanitary sewer overflows along the South Delaware Street area
Expected Impacts: Short term traffic and pedestrian impacts during construction
Notice of Intent/Availability: Addendum Initial Study/Mitigated Negative Declaration Addendum
General Contractor: To be determined
Project Manager:
Martin Quan, Associate Engineer
(650) 522-7330
Sign Up for Future Updates
Please share your contact information through
Notify Me. By sharing your information, we can update you on future opportunities to stay engaged in the outreach effort.