Kingridge Sewer Line
Kingridge Sewer_Phase IName of Project: Kingridge Sewer Line

Impacted Areas: Kingridge Drive

Expected to Commence: Construction will be completed in phases.  The first and second phases were completed in January 2011 and February 2012.  The third phase is anticipated to commence in Summer 2014.

Expected to Finish: Expected Summer 2015, dependent on environmental permits.

Work Hours: To be determined. However, 8:00am – 5:00pm, Monday - Friday, is anticipated.

Short Description of Work: Rehabilitate sanitary sewer line in Kingridge Canyon. Construction includes stabilization of the pipe’s foundation within the Canyon.

Kingridge Sewer_Phase 1Benefits of Work: Reduce chances of sanitary sewer overflows

Expected Impacts: Traffic disruption and noise during construction

General Contractor: Phase III contractor to be determined. 

Kingridge Sanitary Sewer Line Improvements - Phase III - Initial Study/Mitigated Negative Declaration (22.5 MB - 207 pages):
Entire document (22.5 MB - 207 pages)
Pages 1-5 (3.95 MB)
Page 6 (8.0 MB)
Pages 7-100 (4.62 MB)
Pages 101-182 (3.37 MB)
Pages 183-207 (2.69 MB)


Project Manager:
  
Jimmy Vo, Associate Engineer
(650) 522-7319
e-mail